Now you try one. We'll walk you through it, step by boring step. Mechanic and Enthusiast entered into a contract under the terms of which Mechanic was to rebuild Enthusiast's engine for a price of $8,000. Mechanic rebuilt the engine, but Enthusiast refused to pay. The court needs to determine how much Mechanic is entitled to. What is Mechanic's loss in value? |
| The cost of rebuilding the engine. |
| $8,000--the amount he was to receive under the contract but didn't get because of the breach. |
| The amount it would have cost Mechanic to rebuild the engine. |