| Is there any "other loss, including incidental or consequential loss, caused by the breach?" (The contract price was $3,000 and it was anticipated that Painter would spend $500 on paint and other materials in the course of performing the contract. Homeowner breached the contract before Painter had done anything.) |
| The "other loss" is $3,000. |
| No. The $3,000 is the "loss in value" that we just calculated. We can't count it twice. |